New construction grandstand stadium in Kassel
In April 2009, it turned out that the grandstand of the Kassel-Aue stadium can no longer be rehabilitated and must be demolished.
The city of Kassel wanted to hold the German track championship there in the year 2011. Therefore, the most rapid and legally reliable implementation of the award procedure possible was very important for the city of Kassel. After the procedure could be concluded within three months, a review procedure and an immediate appeal led to a delay of three months. The bid could be accepted at the beginning of 2010.
Our services
We designed and provided support for the Europe-wide award procedure for the city of Kassel. We also assumed the contract design and provided support to the city of Kassel in the contract negotiations and represented it before the Higher Regional Court.
Responsible for the project:
Dr. Ute Jasper, Düsseldorf